Material Management – MCQ from Study Material (Basic)

Comprehensive Multiple Choice Questions (MCQs) based on the Material Management, covering all 12 chapters including Introduction, Procurement Policy, Methods of Procurement (IFD, Rate Contracts, Direct Purchase, Global Tenders), EMD & Performance Security, Tender Evaluation & TPC Procedures, Contract Placement, Import Procurement, Delivery Period Management, Liquidated Damages, Force Majeure, Receipt & Inspection of Stores, Payment of Bills, and Arbitration/Dispute Settlement. Essential study material for government employees across departments preparing for Limited Departmental Competitive Examination (LDCE), promotion tests, and procurement-related assessments. Aligned with DGS&D practices, Defence Procurement Manual-2005 guidelines, and financial propriety principles applicable to public sector procurement.

Study Material Links:

Material Management

1 / 30

According to the Government Purchase Policy, what preference can be granted to Central Public Sector Enterprises (CPSEs)?

2 / 30

What is the recommended course of action when post-tender negotiations are deemed necessary?

3 / 30

How should disputes with Public Sector Undertakings (PSUs) be handled initially?

4 / 30

In case of procurement from overseas suppliers, what does 'F.O.B.' stand for?

5 / 30

What is the purpose of the 'Force Majeure' clause in a contract?

6 / 30

When can a repeat order be placed on a supplier?

7 / 30

What is the primary reason for constituting Tender Purchase Committees (TPCs)?

8 / 30

What is a 'severable' contract?

9 / 30

What is the purpose of vendor evaluation?

10 / 30

Who is considered the 'purchaser' in all cases of defence procurement according to the manual?

11 / 30

Which of the following is NOT a method of procurement mentioned in the manual?

12 / 30

What is the purpose of preparing a Store Holder Inability Sheet (SHIS)?

13 / 30

What action should be taken if a successful tenderer fails to furnish the required Performance Security Deposit?

14 / 30

In the event of a single valid quote being received against a Limited Tender Enquiry (LTE), how should the case be progressed?

15 / 30

What is the primary role of the Authority Holding Sealed Particulars (AHSP)?

16 / 30

If a dispute arises from a contract that includes the standard arbitration clause, who is responsible for appointing the Sole Arbitrator?

17 / 30

What is the standard payment term for contracts as per the General Conditions of contract mentioned in the manual?

18 / 30

A 'Force Majeure' clause is intended to provide relief from contractual obligations due to what kind of circumstances?

19 / 30

In a Limited Tender Enquiry (LTE), what is the normal minimum number of suppliers to whom the enquiry should be sent?

20 / 30

How are tenders received after the specified time for opening treated?

21 / 30

What is the standard rate for recovering Liquidated Damages (LD) for delayed delivery of stores?

22 / 30

What is the standard grace period automatically available in contracts for the delivery of stores?

23 / 30

According to the manual, what is the 'essence of the contract' in relation to supply timelines?

24 / 30

What is the preferred rate for Performance Security Deposit payable by a supplier?

25 / 30

What is the standard quantum of Earnest Money Deposit (EMD) to be charged from tenderers who are not registered?

26 / 30

Under what circumstances may procurement from a single source (Single Tender) be resorted to?

27 / 30

For indigenously available direct materials, what is the maximum provisioning period for which action can be taken?

28 / 30

What is a Rate Contract (RC) as defined in the manual?

29 / 30

What is the definition of 'Stores' as described in the manual?

30 / 30

According to the manual, what is the primary purpose of the 'Material Management and Procurement Manual' for Ordnance Factories?

Your score is

The average score is 59%

0%

Disclaimer:

This website is an independent educational resource intended solely for practice purposes. The questions and answers provided here are based on general study materials and do not represent official exam content or an authentic answer key. As our team manually enters MCQ questions into the database and the system generates tests automatically, minor errors may occasionally occur. We are not responsible for any issues arising from such errors. In case you encounter any discrepancy, please report the specific question via email or through the ‘Contact Us’ page, or use your own knowledge to evaluate it. ldcemocktest.in does not earn any revenue from this platform—it is a completely free service provided to support learners. This website assumes no liability whatsoever for any consequences resulting from the use of its content.